Spain's 80% hourly rule: which solar plants can supply a data centre

How an operating Spanish solar plant can contribute to a data centre’s renewable supply under Real Decreto 1032/2026, and what to prepare for a buyer.

Also available in Español

PV8 calculatorTry it on your plantEstimate how much of a reference buyer’s hourly target your available solar output can cover. Compare storage and wind with the same plant. No registration required.

Can an existing plant qualify?

Real Decreto 1032/2026 was published in the BOE on 21 November and took effect on 22 November 2026. Under Article 7.9, a PV plant of any age can count towards a data centre’s additionality requirement if it had no signed forward renewable electricity purchase agreement (PPA) on that date.

Check the contracts in force on 22 November and how much output you can offer now or at a future delivery date. A contract that has since expired still matters for the historical test.

What does the buyer need?

The grid-access threshold is 10 MW or more for the data centre. Centres at the same location under the same ownership are assessed together. The provisions cover applications and projects with access rights that have yet to connect. The threshold is on the buyer’s side, so a smaller solar plant can supply part of the portfolio.

Article 7 tests eligible generation against 80% of total consumption. Article 8 separately requires at least 80% of consumption in each hour to have renewable backing in that hour under the general route. The buyer can combine several qualifying sources.

How many MWh can the plant contribute?

For a buyer drawing 12 MW continuously, the hourly target is 9.6 MWh. If the buyer has already secured 4 MWh in a particular hour, up to 5.6 MWh of available solar export can close that hour’s gap. Repeat for every hour and add those contributions.

PV8’s illustrative 40 MWp plant generates 64 GWh in a modelled year. With all output available and no other supply at the reference buyer, about 34.2 GWh contributes to the hourly target. Align actual export and the buyer’s remaining need by timestamp to refine the estimate. Storage can shift energy into later hours, subject to available charge, losses and the accounting in Article 8.5.

When does the buyer’s target change?

The first transitional provision allows qualifying centres entering operation before 31 December 2030 to opt into SRAP, the automatic power-reduction scheme. During the five-year transition from entry into force, the target is 60% in each P1 hour through 2028, then 70% in each P1 hour and 60% in each P2 hour. Technical qualification and priority disconnection apply.

Article 9 sets buyer compensation separately for annual additionality and monthly hourly-correlation deviations. On the general route the latter uses the average severity of hourly shortfalls and rates of €2, €5, €8, €11 or €16 per MWh consumed when there is a deviation. Any seller price depends on the contract.

What to prepare for the first buyer conversation

  1. Gather the commissioning certificate, PPA history, export-meter data and evidence of the share available for delivery. If applicable, include the revised connection agreement and storage metering.
  2. Identify the buyer, delivery start, plants, hourly coverage method and expected volume. Article 11 requires a term of at least six years, a public deed and redemption of the associated guarantees of origin at least annually against the buyer’s supply-point identifier (CUPS).
  3. Send an initial supply profile with the assumptions, the hours where energy is still needed and the evidence both parties must confirm. The calculator can prepare a first comparison before either party shares commercial details.

Sources

Did this answer your question?

Your response helps PV8 improve the next guide.

Still need a hand?

Bring the decision, not a support ticket.

Tell PV8 what you are trying to decide and which asset or result is involved.
Contact PV8 →