How much could your solar plant supply to a data centre?
For data centres in scope with at least 10 MW of grid access, the general rule requires renewable backing for 80% of consumption in each hour.
Model your plant
Start with the example or enter your own figures.
How much would wind or storage add?
Same plant and buyer. Each alternative uses 20 MW of wind or a 20 MW / 80 MWh battery where shown. Extra MWh are measured against solar alone.
| Supply | MWh to target | Extra MWh | MWh missing | Hours at target |
|---|---|---|---|---|
| Solar alone | 34,248 | 0 | 49,848 | 2,569 |
| Solar + storage | 50,668 | 16,421 | 33,428 | 4,479 |
| Solar + wind | 55,088 | 20,840 | 29,008 | 4,201 |
| Solar + wind + storage | 68,841 | 34,593 | 15,255 | 6,533 |
Inspect the hourly simulation
Selected supply covers the target in 2,569 of 8,760 hours. The remaining energy needed to reach the hourly target is 49,848 MWh.
- Backed
- Short, darker the further
- Outside the route's periods
Days run left to right from 1 January, hours (solar time) top to bottom from midnight. Select a day, or use the arrow keys on the map, to see its hours below.
Energy missing to reach the 80% share in each hour, summed over the year, on the standard route. Hours are solar time.
- Solar
- Wind
- Battery discharging
- Battery charging
- Data-centre load
- Share to back
Article 9 · Illustrative monthly compensation on the ordinary route, assuming the selected supply is the buyer’s entire eligible portfolio.
Separate annual additionality illustration under Article 9: if all selected generation qualifies, its production is 60.9% of the buyer’s annual consumption. The implied rate is 6 €/MWh on 105,120 MWh, or €630,720. Provisional billing uses the previous calendar year, followed by reconciliation.
| Month | Hours backed | Shortfall | Rate (€/MWh) | Amount (€) |
|---|---|---|---|---|
| January | 82 | 66.5% | 16 | 142,848 |
| February | 182 | 61% | 16 | 129,024 |
| March | 269 | 57.7% | 16 | 142,848 |
| April | 270 | 56% | 16 | 138,240 |
| May | 279 | 54.8% | 16 | 142,848 |
| June | 302 | 54.2% | 16 | 138,240 |
| July | 279 | 54.5% | 16 | 142,848 |
| August | 279 | 55.5% | 16 | 142,848 |
| September | 270 | 57% | 16 | 138,240 |
| October | 229 | 59.6% | 16 | 142,848 |
| November | 126 | 64.6% | 16 | 138,240 |
| December | 2 | 69.8% | 16 | 142,848 |
For the selected mix, the monthly average hourly shortfall determines the Article 9 rate, applied to total monthly consumption. Eligibility, actual metering and other purchases affect settlement.
- The route's periods are clock hours from the Peninsula's toll calendar; the modelled day is solar time, which runs about one hour behind the clock in winter and two in summer. Holidays are the fixed national dates.
Prepare a buyer discussion
Save your figures in a buyer brief or ask PV8 to review the plant and the evidence needed for a contract.
Opens PV8's registration. Your interest in data centres in Spain carries over; your plant figures do not.
For assets larger than 10 MWp, an analyst can review the contract and hourly data with you. Request a plant review.
The calculation runs in your browser and sends no figures to PV8; a link that holds them does reach the server's logs. Server logs and usage events are covered by the Privacy Notice.
Review my plant with PV8
Tell us about the asset or buyer. You can see exactly which figures will be sent below.
Developing a data centre and looking for supply that counts? Use the same form
What this result rests on
- Rule status
- In force
- Instrument
- Real Decreto 1032/2026, de 20 de noviembre
Evidence needed for a contract
Verify hourly net export, existing commitments, the commissioning record and the buyer’s access contract. Article 11 requires a contract of at least six years, executed as a public deed, identifying the buyer, plants, coverage formula and volumes, with annual redemption of guarantees of origin against the buyer’s CUPS.
Official decree · Articles 2, 7–9 and 11 and first transitional provision
The solar shape is modelled. The wind is the 2023 ERA5 reanalysis for one site in the Ebro valley (Aragón), through a published turbine power curve, set to the Spanish wind fleet's average output that year. It stands in for wind anywhere in Spain, so your site's wind will differ: in September and October this site ran at about half the fleet's level. Neither is your plant's metered data. The test covers every hour of the year. Wind data: ECMWF, Copernicus Climate Change Service, CC BY 4.0 (creativecommons.org/licenses/by/4.0). Contains modified Copernicus Climate Change Service information 2023; neither the European Commission nor ECMWF is responsible for any use made of it.
This is a screening result, not legal advice. The published text and your contracts decide what counts.
PV8 uses specialist engineering and commercial engines to uncover and test new value routes for operating PV assets and ready-to-build projects.
Read the guide: Spain's 80% hourly rule and which solar plants can supply a data centre →