How much could your solar plant supply to a data centre?

For data centres in scope with at least 10 MW of grid access, the general rule requires renewable backing for 80% of consumption in each hour.

Royal Decree 1032/2026 · In force since 22 November 2026

Model your plant

Start with the example or enter your own figures.

Your solar plant

Installed DC capacity.

Use metered export if available.

Exclude output already committed.

Modelled year · PV alone

Contribution to the buyer’s hourly target

34,248 MWh

Annual contribution from 64,000 MWh available, assuming a buyer with a constant 12 MW load.

The buyer still needs 49,848 MWh in other hours. Your plant has 29,752 MWh available above this buyer’s hourly target.

Eligibility pending. Check the PPA on 22 November 2026 and the commissioning dates. The figures show a physical contribution only.

Request a plant reviewPrepare buyer brief

The data centre
Check contract eligibility
On 22 November 2026, was the plant covered by a signed forward contract for the purchase of renewable electricity (PPA)?

The ordinary 36-month test compares plant commissioning with the buyer’s access contract or first use of the energy. For repowering, verify the substantial revision of the connection agreement and relevant dates.

Change the supply mix or test the flexible route
Added supply

Set optional equipment for the detailed simulation. The comparisons also show standalone alternatives when the selected capacities are zero.

The flexible route

During the five-year transition, an eligible centre in SRAP must be able to reduce its load to zero when instructed. The hourly targets depend on the year and toll period.

Rule in force

How much would wind or storage add?

Same plant and buyer. Each alternative uses 20 MW of wind or a 20 MW / 80 MWh battery where shown. Extra MWh are measured against solar alone.

SupplyMWh to targetExtra MWhMWh missingHours at target
Solar alone34,248049,8482,569
Solar + storage50,66816,42133,4284,479
Solar + wind55,08820,84029,0084,201
Solar + wind + storage68,84134,59315,2556,533
Inspect the hourly simulation

Selected supply covers the target in 2,569 of 8,760 hours. The remaining energy needed to reach the hourly target is 49,848 MWh.

Article 9 · Illustrative monthly compensation on the ordinary route, assuming the selected supply is the buyer’s entire eligible portfolio.

Separate annual additionality illustration under Article 9: if all selected generation qualifies, its production is 60.9% of the buyer’s annual consumption. The implied rate is 6 €/MWh on 105,120 MWh, or €630,720. Provisional billing uses the previous calendar year, followed by reconciliation.

Month by month on the standard route
MonthHours backedShortfallRate (€/MWh)Amount (€)
January8266.5%16142,848
February18261%16129,024
March26957.7%16142,848
April27056%16138,240
May27954.8%16142,848
June30254.2%16138,240
July27954.5%16142,848
August27955.5%16142,848
September27057%16138,240
October22959.6%16142,848
November12664.6%16138,240
December269.8%16142,848

For the selected mix, the monthly average hourly shortfall determines the Article 9 rate, applied to total monthly consumption. Eligibility, actual metering and other purchases affect settlement.

  • The route's periods are clock hours from the Peninsula's toll calendar; the modelled day is solar time, which runs about one hour behind the clock in winter and two in summer. Holidays are the fixed national dates.

Prepare a buyer discussion

Save your figures in a buyer brief or ask PV8 to review the plant and the evidence needed for a contract.

For assets larger than 10 MWp, an analyst can review the contract and hourly data with you. Request a plant review.

The calculation runs in your browser and sends no figures to PV8; a link that holds them does reach the server's logs. Server logs and usage events are covered by the Privacy Notice.

Review my plant with PV8

Tell us about the asset or buyer. You can see exactly which figures will be sent below.

PV8 will receive your name, your e-mail and this text:


PV8 stores this message and uses it to reply to you. Privacy Notice

Developing a data centre and looking for supply that counts? Use the same form

What this result rests on

Rule status
In force
Instrument
Real Decreto 1032/2026, de 20 de noviembre

Evidence needed for a contract

Verify hourly net export, existing commitments, the commissioning record and the buyer’s access contract. Article 11 requires a contract of at least six years, executed as a public deed, identifying the buyer, plants, coverage formula and volumes, with annual redemption of guarantees of origin against the buyer’s CUPS.

Official decree · Articles 2, 7–9 and 11 and first transitional provision

The solar shape is modelled. The wind is the 2023 ERA5 reanalysis for one site in the Ebro valley (Aragón), through a published turbine power curve, set to the Spanish wind fleet's average output that year. It stands in for wind anywhere in Spain, so your site's wind will differ: in September and October this site ran at about half the fleet's level. Neither is your plant's metered data. The test covers every hour of the year. Wind data: ECMWF, Copernicus Climate Change Service, CC BY 4.0 (creativecommons.org/licenses/by/4.0). Contains modified Copernicus Climate Change Service information 2023; neither the European Commission nor ECMWF is responsible for any use made of it.

This is a screening result, not legal advice. The published text and your contracts decide what counts.